Regulation Of The Electric Power Industry
12 minutes • 2470 words
Table of contents
Section 38. Creation of the ERC
An independent, quasi-judicial regulatory body called the Energy Regulatory Commissions (ERC) is created.
It is composed of:
- 1 Chairman
- 4 members to be appointed by the President
They shall be:
- natural-born citizens
- residents of the Philippines
- persons of good moral character
- at least 35 years old
- of recognized competence in any of the following fields:
- energy
- law
- economics
- finance
- commerce
- engineering
- have at least 3 years distinguished experience in their respective fields of expertise as long as out of the 4 members, at least:
- 1 shall be a member of the Philippine Bar with at least 10 years experience in the active practice of law
- 1 shall be a certified public accountant with at least ten (10) years experience in active practice.
Within 3 months from the creation of the ERC, the Chairman shall submit for the approval by the President the new organizational structure and plantilla positions necessary to carry out the powers and functions of the ERC.
The Chairman of the Commission, who shall be a member of the Philippine Bar, shall act as the CEO of the Commission.
All members of the Commission shall have a term of seven (7) years: Provided, That for the first appointees, the Chairman shall hold office for seven (7) years, two (2) members shall hold office for 5 years and the other 2 members shall hold office for 3 years; Provided, further, That appointment to any future vacancy shall only be for the unexpired term of the predecessor: Provided, finally, That there shall be no reappointment and in no case shall any member serve for more than seven (7) years in the Commission.
The Chairman and members of the Commission shall assume office of the beginning of their terms, and the current Board and existing personnel of ERB shall continue to hold office, as long as:
- the Commission has not been constituted
- the new staffing pattern and plantilla positions have not been approved and filled-up
The existing personnel of the ERB, if qualified, shall be preferred to fill up of plantilla positions created in the ERC, subject to existing civil service rules and regulations.
Members of the Commission:
- shall enjoy security of tenure
- shall not be suspended or removed from office except for just cause as specified by law.
The Chairman and members of the Commission or any of their relatives within the fourth civil degree of consanguinity or affinity, legitimate or common law, shall be prohibited from holding any interest either as investor, stockholder, officer or director, in any company or entity engaged in the business of transmitting, generating, supplying or distributing any form of energy and must, therefore, divest through sale or legal disposition of any and all interests in the energy sector upon assumption of office.
3 members of the Commission shall constitute a quorum.
The majority vote of 2 members in a meeting in a quorum is needed to adopt any rule, ruling, order, resolution, decision, or other act of the Commission in the exercise of its quasi-judicial functions as long as:
- in fixing rates and tariffs, an affirmative vote of 3 members shall be required.
Section 39. Compensation and Other Emoluments for ERC Personnel
The compensation and other emoluments for the Chairman and members of the Commission and the ERC personnel shall be exempted from the coverage of Republic Act No. 6758, otherwise known as the “Salary Standardization Act”.
For this purpose, the schedule of compensation of the ERC personnel, except for the initial salaries and compensation of the Chairman and members of the Commission, shall be submitted for approval by the President of the Philippines.
The new schedule of compensation shall be implemented within 6 months from the effectivity of this Act and may be upgraded by the President of the Philippines as the need arises: Provided, That in no case shall the rate be upgraded more than once a year.
The Chairman and members of the Commission shall initially be entitled to the same salaries, allowances and benefits as those of the Presiding Justice and Associate Justices of the Supreme Court, respectively.
The Chairman and the members of the Commission shall, upon completion of their term orupon becoming eligible for retirement under existing laws, be entitled to the same retirement benefits and the privileges provided for the Presiding Justice and Associate Justices of the Supreme Court, respectively.
Section 40. Enhancement of Technical Competence
The ERC shall establish rigorous training programs for its staff for the purpose of enhancing the technical competence of the ERC in the following areas: evaluation of technical performance and monitoring of compliance with service and performance standards, performance-based rate-setting reform, environmental standards and such other areas as will enable the ERC to adequately perform its duties and functions.
Section 41. Promotion of Consumer Interests
The ERC shall handle consumer complaints and ensure the adequate promotion of consumer interests.
Section 42. Budget of the ERC
150m pesos is the intial budget of the ERC.
Any balance shall initially be sourced from the Office of the President of the Philippines. Thereafter, the annual budget of the ERC shall be included in the regular or special appropriations.
Section 43. Functions of the ERC
The ERC shall promote competition, encourage market development, ensure customer choice and penalize abuse of market power in the restructured electricity industry.
In appropriate cases, the ERC is authorized to issue cease and desist order after due notice and hearing. Towards this end, it shall be responsible for the following key functions in the restuctured industry:
- Enforce the implementing rules and regulations of this Act
- Within six (6) months from the effectivity of this Act, promulgate and enforce, in accordance with law, a National Grid Code and a Distribution Code which shall include, but not limited to, the following: (i) Performance standards for TRANSCO O & M Concessionaire, distribution utilities and suppliers: Provided, That in the establishment of the performance standards, the nature and function of the entities shall be considered; and (ii) Financial capability standards for the generating companies, the TRANSCO, distribution utilities and suppliers: Provided, further, That such standards are set to ensure that the electric power industry participants meet the minimum financial standards to protect the public interest. Determine, fix, and approve, after due notice and public hearings the universal charge, to be imposed on all electricity end-users pursuant to Section 34 hereof. (c) Enforce the rules and regulations governing the operations of the electricity spot market and the activities of the spot market operator and other participants in the spot market, for the purpose of ensuring a greater supply and rational pricing of electricity; (d) Determine the level of cross subsidies in the existing retail rate until the same is removed pursuant to Section 74 hereof; (e) Amend or revoke, after due notice and hearing, the authority to operate of any person or entity which fails to comply with the provisions hereof, the IRR or any order or resolution of the ERC. In the event a divestment is required, the ERC shall allow the affected party sufficient time to remedy the infraction or for an orderly disposal, but in no case exceed twelve (12) months from the issuance of the order; (f) In the public interest, establish and enforce a methodology for setting transmission and distribution wheeling rates and retail rates for the captive market of a distribution utility, taking intro account all relevant considerations, including the efficiency or inefficiency of theregulated entities. The rates must be such as to allow the recovery of just and reasonable costs and a reasonable return on rate base (RORB) to enable the entity to operate viably. The ERC may adopt alternative forms of internationally-accepted rate-setting methodology as it may deem appropriate. The rate-setting methodology so adopted and applied must ensure a reasonable price of electricity. The rates prescribed shall be non-discriminatory. To achieve this objective and to ensure the complete removal of cross subsidies, the cap on the recoverable rate of system losses prescribed in Section 10 of Republic Act No. 7832, is hereby amended and shall be replaced by caps which shall be determined by the ERC based on load density, sales mix, cost of service, delivery voltage and other technical considerations it may promulgate. The ERC shall determine such form or rate-setting methodology, which shall promote efficiency. In case the rate setting methodology used is RORB, it shall be subject to the following guidelines: (i) For purposes of determining the rate base, the TRANSCO or any distribution utility may be allowed to revalue its eligible assets not more than once every three (3) years by an independent appraisal company: Provided, however, That ERC may give an exemption in case of unusual devaluation: Provided, further, That the ERC shall exert efforts to minimize price shocks in order to protect the consumers; (ii) Interest expenses are not allowable deductions from permissible return on rate base; (iii) In determining eligible cost of services that will be passed on to the end-users, the ERC shall establish minimum efficiency performance standards for the TRANSCO and distribution utilities including systems losses, interruption frequency rates, and collection efficiency; (iv) Further, in determining rate base, the TRANSCO or any distribution utility shall not be allowed to include management inefficiencies like cost of project delays not excused by force majeure, penalties and related interest during construction applicable to these unexcused delays; and (v) Any significant operating costs or project investments of the TRANSCO and distribution utilities which shall become part of the rate base shall be subject to verification by the ERC to ensure that the contracting and procurement of the equipment, assets and services have been subjected to transparent and accepted industry procurement and purchasing practices to protect the public interest. (g) Three (3) years after the imposition of the universal charge, ensure that the charges of the TRANSCO or any distribution utility shall bear no cross subsidies between grids, within grids, or between classes of customers, except as provided herein; (h) Review and approve any changes on the terms and conditions of service of the TRANSCO or any distribution utility; (i) Allow the TRANSCO to charge user fees for ancillary services to all electric power industry participants or self-generating entities connected to the grid. Such fees shall be fixed by the ERC after due notice and public hearing; (j) Set a lifeline rate for the marginalized end-users; (k) Monitor and take measures in accordance with this Act to penalize abuse of market power, cartelization, and anti-competitive or discriminatory behavior by any electric power industry participant; (l) Impose fines or penalties for any non-compliance with or breach of this Act, the IRR of this Act and the rules and regulations which it promulgates or administers;(m) Take any other action delegated to it pursuant to this Act; (n) Before the end of April of each year, submit to the Office of the President of the Philippines and Congress, copy furnished the DOE, an annual report containing such matters or cases which have been filed before or referred to it during the preceding year, the actions and proceedings undertaken and its decision or resolution in each case. The ERC shall make copies of such reports available to any interested party upon payment of a charge which reflects the printing costs. The ERC shall publish all its decisions involving rates and anti- competitive cases in at least one (1) newspaper of general circulation, and/or post electronically and circulate to all interested electric power industry participants copies of its resolutions to ensure fair and impartial treatment; (o) Monitor the activities in the generation and supply of the electric power industry with the end in view of promoting free market competition and ensuring that the allocation or pass through of bulk purchase cost by distributors is transparent, non-discriminatory and that any existing subsidies shall be divided pro-rata among all retail suppliers; (p) Act on applications for or modifications of certificates of public convenience and/or necessity, licenses or permits of franchised electric utilities in accordance with law and revoke, review and modify such certificates, licenses or permits in appropriate cases, such as in cases of violations of the Grid Code, Distribution Code and other rules and regulations issued by the ERC in accordance with law; (q) Act on applications for cost recovery and return on demand side management projects; (r) In the exercise of its investigative and quasi-judicial powers, act against any participant or player in the energy sector for violations of any law, rule and regulation governing the same, including the rules on cross-ownership, anti-competitive practices, abuse of market positions and similar or related acts by any participant in the energy sector or by any person, as may be provided by law, and require any person or entity to submit any report or data relative to any investigation or hearing conducted pursuant to this Act; (s) Inspect, on its own or through duly authorized representatives, the premises, books of accounts and records of any person or entity at any time, in the exercise of its quasi-judicial power for purposes of determining the existence of any anti-competitive behavior and/or market power abuse and any violation of rules and regulations issued by the ERC; (t) Perform such other regulatory functions as are appropriate and necessary in order to ensure the successful restructuring and modernization of the electric power industry, such as, but not limited to, the rules and guidelines under which generation companies, distribution utilities which are not publicly listed shall offer and sell to the public a portion not less than fifteen percent (15%) of their common shares of stocks: Provided, however, That generation companies, distribution utilities or their respective holding companies that are already listed in the PSE are deemed in compliance. For existing companies, such public offering shall be implemented not later than five (5) years from the effectivity of this Act. New companies shall implement their respective public offerings not later than five (5) years from the issuance of their certificate of compliance; and (u) The ERC shall have the original and exclusive jurisdiction over all cases contesting rates, fees, fines and penalties imposed by the ERC in the exercise of the above mentioned powers, functions and responsibilities and over all cases involving disputes between and among participants or players in the energy sector. All notices of hearings to be conducted by the ERC for the purpose of fixing rates or fees shall be published at least twice for two successive weeks in two (2) newspapers of nationwide circulation.SEC. 44. Transfer of Powers and Functions. – The powers and functions of the Energy Regulatory Board not inconsistent with the provisions of this Act are hereby transferred to the ERC. The foregoing transfer of powers and functions shall include all applicable funds and appropriations, records, equipment, property and personnel as may be necessary.